The 2026 programme by the numbers
Announced in May 2026, this is one of the largest single-year construction commitments in the brand’s history — and the published split tells owners something useful before they ever sit down with corporate.
| Total programme investment | $400M |
| Contributed by franchise owners | $270M |
| Contributed by Tim Hortons | $130M |
| Restaurants renovated | 400 |
| New restaurants built | 80 |
| Owners participating | 340 |
| Ontario projects | 214 · $165M |
The single most important figure there is the split. Corporate is publicly carrying roughly a third. That is a disclosed baseline you can reference in your own conversation, which owners in previous cycles did not have.
So what does one restaurant cost?
The programme total does not divide cleanly, and you should be sceptical of anyone who pretends it does. Spread across all 480 projects, the owner contribution averages roughly $562,000. But 80 of those projects are ground-up builds, which cost far more than a renovation. Strip those out and the renovation figure sits meaningfully below that average.
The clearest per-restaurant number ever reported publicly comes from the previous cycle. In 2018, when Tim Hortons announced a $700 million plan to renovate nearly every Canadian location, the cost to an individual restaurant owner was reported at approximately $450,000.
Two scope tiers, very different bills
Tim Hortons renovations are not one thing. The programme runs on two tiers, and which one you are assigned changes the cost dramatically:
- 10-Year Refresh. Exterior upgrades plus interior finish updates to public areas, service areas, washrooms and furnishings. Cosmetic and finish-led.
- 20-Year Full Renovation. A complete redesign of public areas, service areas, washrooms and back of house, plus exterior work. This one moves walls and touches your kitchen.
A full renovation reaching back of house is a different category of project entirely. It means equipment, mechanical and electrical, longer closure, and far more that can be discovered once the walls are open. Confirm which tier applies to you in writing before you price anything.
The part the announcement does not cover
In 2018 the programme generated real friction. The Great White North Franchisee Association — representing roughly half of Canadian franchisees at the time — advised members not to sign or agree to anything until more detail was disclosed, and argued that the parent company wanted to solve a sales problem by having owners spend while it contributed little. The company said costs would be split on historical proportions but declined to specify them.
Whatever your view of that dispute, the lesson is practical: the split is the number that matters, and it is negotiable territory. The headline programme figure tells you almost nothing about your own obligation.
The costs in no announcement
- Lost trading days — usually the largest line item, and it appears in no bid
- Electrical service upgrades if new equipment exceeds your existing panel
- Code deficiencies exposed once walls are opened in an older building
- Permit and inspection time, which varies enormously by municipality
- Landlord consent and any base building work your lease assigns to you
- Staff retention through a closure